Australia’s energy giant Woodside is moving its $17.5 billion LNG development project in Calcasieu Parish closer to a 2029 first cargo date with a new construction milestone, reports Offshore Energy.
The project was 28 percent complete at the end of the second quarter of 2026 as buildout activities gather pace. Since announcing a final investment decision (FID) more than 14 months ago, activities at the site have ramped up, with two massive LNG storage tanks and three LNG trains currently under construction. Woodside confirms that the project remains on budget. Read more from Offshore Energy.